Investment Analysis And Lookheed Tri Star Case Study
Investment analysis and Lockheed Tri Star
- Rain bow products are considering the purchase of a paint-mixing machine to reduce labor costs. The saving are expected to results in additional cash flow to rainbow of 5000 per year. The machine costs $35000 and is expected to last for 15 years. Rainbow has determined that the cost of capital for such investment is 12%.
- Solution: additional cash flow= $5000
Machine cost = $35000
Life of machine = 15 years
Cost of capital = 12%
Payback period = cost of investment/annual cash flow
Payback period = 35000/5000 = 7 years
This show that amount of investment can be pay back in 7 years which is less than the life of machine so according to payback period we adopt this investment.
NPV = net cash flow* (1-(1+ cost of capital)^no of years)/cost of capital – investment
NPV = 5000*(1-(1+0.12)^-15)/0.12- 35000= -946
Negative NPV show that company should not accept the project due to negative impact of investment.
IRR is less than cost of capital, because the IRR must be consider when the NPV of the project should be zero but in some other case the IRR is not considerable.
- Solution: rainbow should not purchase the machine with the contract because it give more negative NPV which show that with this service purchasing is not beneficial for the company.
- Growing rate = 4%
Discount rate= 20%
Amount of perpetuity = $5000
Present value = amount of pertputity/ discount rate – growing rate
Present value = 31250
Npv= pv- investment= 31250-35000= -3750
So in this option again we get negative npv which show that this investment opportunity is not favorable for the company and company should not waste its money by investing such project.
- NPV of four projects: where discount rate is 15 %
- Add a new window: NPV = {R1/(1+i) +R2/(1+i)^2+R3/(1+i)^3}- investment
NPV = {44000/(1+0.15)+44000/(1+0.15)^2+44000/(1+0.15)^3- 75000
NPV = 25460
- Update existing equipment: NPV = {R1/(1+i) +R2/(1+i)^2+R3/(1+i)^3}- investment
NPV = {23000/(1+0.15)+23000/(1+0.15)^2+23000/(1+0.15)^3- 50000
NPV = 2513
- Build a new stand:
NPV = {R1/(1+i) +R2/(1+i)^2+R3/(1+i)^3}- investment
NPV = {70000/ (1+0.15) +70000/ (1+0.15) ^2+70000/ (1+0.15) ^3- 125000
NPV = 34824
- Rent a larger stand:
NPV: {R1/ (1+i) +R2/(1+i)^2+R3/(1+i)^3}- investment
NPV = {12000/ (1+0.15) +13000/ (1+0.15) ^2+14000/ (1+0.15) ^3- 1000
NPV = 28468
After calculating the NPVs of all options we have to select that option which give maximum NPV. Build a new stand give us maximum NPV so we have to select that option.
- IRR of four projects:
- Add a new window:
IRR = 15%+npv@15 %/( +npv @ 15 %-( -npv@35%))*(35%-15%)
IRR = 0.15+25460/(25460+383)*0.20 = 34.7%
- Updating existing equipment:
IRR = 15%+npv@15 %/( +npv @ 15 %-( -npv@35%))*(35%-15%)
IRR = 15%+2513/(2513+10995)*20% = 18.7%
iii. Build a new stand:
IRR = 15%+npv@15 %/( +npv @ 15 %-( -npv@35%))*(35%-15%)
IRR = 15%+34824/(34824+6291)*20% = 31.9%
Iv: rent a larger stand:
IRR = 15%+npv@15 %/( +npv @ 15 %-( -npv@35%))*(35%-15%)
IRR = 15%+28468(28468-12711)*20% =51.1%
According to IRR lowest percentage option will be selected so company has to move towards updating the existing equipment.
In both methods, IRR and NPV, most suitable and most convenient method is NPV because it easy to calculate and provide a appropriate answers in any type of business, mostly managers concern with NPV while selecting any investment option for the company.
- Which of the four subsidy plans would be recommend to the city if the appropriate discount rate is 20%?
- Subsidize the project to bring its IRR to 25%: as we know the discount rate of MBAT is 20% so its IRR is higher than its discount rate which is consider not too much favorable for the city. Less IRR is most suitable in any investment. So City would not select that suggestion from the MBAT as subsidize by city . this IRR also show that at this rate the NPV of the project going to be zero which create no profit no loss situation for the company.
- Subsidize the project to provide a two year payback: with 20% discount rate,MBAT subsidize with two year pay back period which means that all payment clear in two years and after that company is freely completing its project this option may not be selected by company because its project is 4 years program with annual cash flow from the MBAT to city company. If the select payback period their amount will be return in two years which may or may not beneficial for city company.
- Subsidize the project to provide an NPV of $ 75000 when cash flow discounted at 20%: company not select this option because the actual npv of the project is higher than $75000 so it show a loss dealing for city company because company get less worth of project instead of original high value.
- Subsidize the project to provide an accounting rate of return of 40%. : this option may consider by company because its accounting return must be higher than discount rate. So it would be profitable for the company and they get high advantages in case of return. So city company has to select fourth option after subsidize the MBAT company.
- What is the net present value of the project?
Cost of investment = $110000
Cash flow of project = $210000
NPV = 210000-110000 = $100000 which is very good amount of net present value so company must adopt that new project and enhance the profitability of the project.
- how many shares of common stock must be issued to raise the required capital?
Required amount = $110000
Price of per share= $100 p.s
Number of shares that issued for the capital = 110000/100= 1100 shares are issued from common stock and at the previous price which give reasonable profit to company.
c.what is the effect of new project on the value of the stock of the existing shareholders, if any?
Ans. When company issue new shares to full fill the capital requirement , the earning is going to increase of the company and shareholders expect to increase their earning also .so project is profit generator for the company as given cash flow against investment is high so earning of existing shareholders must be increase with reasonable percentage.
- Forecasted cash flow of the project.
year | 1967 | 1968 | 1969 | 1970 | 1971 | 1972 | 1973 | 1974 | 1975 | 1976 |
Revenue(millions) | 140 | 140 | 420 | 509 | 93 | 93 | 93 | 93 | 93 | 93 |
Production Costs(million) | 100 | 200 | 200 | 200 | 200 | 98 | 98 | 98 | 98 | 98 |
Profit of company | 40 | -60 | -220 | 309 | -107 | -5 | -5 | -5 | -5 | -5 |
Production margin | 71.42% | 142% | 47.6% | 39.29% | 215% | 105% | 105% | 105% | 105% | 105% |
- What is the IRR of the project?
The IRR of the project is more than 10% of cost of capital of the company. Internal rate of return is describing the link with NPV with the projects. Simple is that IRR is not too much important measurement which any company considered in case of selection of projects. So mostly this measurement is not considered in the companies. Instead of this companies use npv measurements which help in providing better decision about the project. But IRR can be calculated with very technical market information.
iii. NPV of the project:
Year | Cash flow | Present value |
1967 | 140/(1+0.10) | 127 |
1968 | 140/(1+0.10)^2 | 115 |
1969 | 420/(1+0.10)^3 | 315 |
1970 | 509/(1+0.10)^4 | 348 |
1971 | 93/(1+0.10)^5 | 58 |
1972 | 93/(1+0.10)^6 | 52 |
1973 | 93/(1+0.10)^7 | 48 |
1974 | 93/(1+0.10)^8 | 43 |
1975 | 93/(1+0.10)^9 | 39 |
1976 | 93/(1+0.10)^10 | 36 |
Present value of project =1181million
Amount of investment = 250million
NPV = 1181-250 = 931million
Which show that project has high npv and this project is very much beneficial for the company. Basically, company cost of capital is very much favorable for the earnings of company so 10% cost of capital is enough earnings which can cover the expenses of company and also generate a high level of profit. Its NPV show that after taking long, its utilization is very much favorable for the company it can bear all its costs and expenses and also generate a high level of profit for the company.